Sl. No | Service Name | Procedure | Checklist | Timeline (Days) |
---|---|---|---|---|
1 | Conversion of Land Use | Click here | Click here | 30 Days |
2 | Building Plan Approval |
1) Online Sanction of Building Plan i) Procedure for Application: Click here ii) Process Map: Click here 2) Inspection Procedure & Checklist for Issuance of Plinth Level Completion Certificate: Click here |
1) Online Sanction of Building Plan i) List of Documents Click here 2) Inspection Procedure & Checklist for Issuance of Plinth Level Completion Certificate: Click here |
Sanction of Building Plan: 30 Days Issuance of Plinth Level Completion Certificate: 7 Days |
3 | Fire Safety Recommendation | Click here | Click here | 60 Days |
4 | Allocation/Permission for Surface Water if Surface Water is the Source | Click here | Click here | 36 Days |
5 | Land Allocation (IDC) | Click here | Click here | 60 Days |
6 | Consent to Establish under Water and Air Act | Click here | Click here | Red- 60 Days, Orange- 30 Days, Green- 15 Days |
7 | Tree Feeling & Tree Transit Permission | Click here | Click here | 90 Days |
8 | Approval of Factory Plan under the Factories ACT 1948 | Click here | Click here | 50 Days |
9 | Mutation of Land | Click here | Click here | 21 Days |
10 | Registration of Property | Click here | Click here | 10 Days |
11 | Drug License | Click here | Click here | 90Days |
12 | Temporary Electricity Connection |
Click here Click here |
Click here Click here |
7 Days |
13 | Permission for extraction of ground water | Click here | Click here | 30 Days to 66 Days depending upon the extraction rate of water |
Note: The above list of State Approvals is comprehensive and no other approvals at present need to be sought for by the Business